@all 13:44 Dec 10, 2020
Vielleicht hilft es, wenn ich sage, dass es um eine Wasserstofftankstelle geht. Equipment means the equipment and materials for the Plant to be supplied by Contractor under the Contract within battery limits, as specified in item ... of the Technical Part. Mechanical Completion means that the erection of the Plant has been completed at Company’s site(s) and pressure tests and test runs of machinery have been carried out successfully, as set forth in item ... of the Technical Part, except for minor items such as painting, minor insulation, cleaning-up and similar matters which do not prevent a safe commissioning and start-up of the Plant and are listed in a punch-list. |